Completing the Hazrat Zeinab Hospital in Ashkezar, Iran
This project started with the efforts of Mr. Ali Akbar Kazemi Ashkezari and in partnership with Omran Boton Alton Co. on approximately 12,000 m2 of built-up area and with 4 floors.
Project specifications:
Executing all architectural operations and mechanical and electrical facilities
Employer: Yazd University of Medical Sciences

Project Identification | |
---|---|
Title | Specifications |
Contract No. & Communication Date | F/198 dated 2018-12-05 |
Employer | Mr. Fazlollah Shekari |
Contract Term | 40 months |
Work values | |||
---|---|---|---|
.No | Description of Operation | Unit | Estimated Amount |
1 | Tile and Ceramic | m2 | 10000 |
2 | Stone | m2 | 12500 |
3 | Brickwork | m2 | 6000 |
4 | Insulation | m2 | 10000 |
5 | Flooring | m2 | 3730 |
6 | Dropped Ceiling | m2 | 4000 |
7 | Floor and Wall Covering | m2 | 6200 |
8 | Plasterwork | m2 | 25000 |