Designing and Building the Parsian Flood Barrier Through Engineering, Procurement, and Construction (EPC)

The engineering design and material and equipment procurement (EPC) of the flood barrier in the Parsian Special Economic Zone included excavation, earth-filling, spreading, water-sprinkling, leveling, compacting, and other operations.

Project specifications:
Designing, procuring materials, and constructing the protective barrier
Employer: Parsian Energy Intensive Industrial Special Economic Zone

p4
Project Identification
TitleSpecifications
Communication Date2019-08-11
EmployerIranian Mines and Mining Industries Development and Renovation Organization
Contract Price975.000.000.000
Contract Term36 months
Project Start Date2018-08-11
Project Completion Date2021-08-11
Work values
No.Description of Operation Unit Estimated Amount
1Excavationm32350,000
2Foundation diggingm370,000
3Sludge removalm3300,000
4Earth-fillingm3200,000
5Revetmentm355,000
6Geotextilem2121,000
7Gabionm355,000